Owner | Teck, Vancouver, BC |
---|---|
Contractor | MDG Contracting Services, Sparwood, BC |
Project | Permanent creek diversion structure, earthen sediment ponds, piping, HDPE liner. |
Contract | Combined lump sum & time/materials. |
Value | $18 million. |
Duration | 11 months. |
Man-Hours | 32,000. |