Owner | Lafarge, Georgia, Atlanta |
---|---|
Contractor | CIF Construction Ltd., Prince George, BC |
Project | Install 16,000 m3 of structural concrete including mill bases, mill baghouse, clinker cooler, kiln foundations and stacker reclaimer. |
Contract | Unit price. |
Value | $25 million. |
Duration | 15 months. |
Man-Hours | 190,000. |